69 kV Transmission Line Project
Bridge Creek
Building a stronger, more resilient electric system for northern Indiana.
- New Substation
- 69/12 kV
- New Transmission Line
- ~5 miles
- Location
- Carroll County, IN
Project Overview
Investing in reliable power for Carroll County
Wabash Valley Power Alliance (WVPA), the not-for-profit power supply partner for Carroll White REMC, is working to improve the reliability and performance of the electric system serving Carroll County. Through long-term infrastructure planning, WVPA is investing to meet today’s energy needs and prepare local communities for the future.
The Bridge Creek Transmission Project involves WVPA constructing and operating a new 69/12 kV substation southeast of Delphi and approximately five miles of new 69 kV transmission line. The project will strengthen the local electric system, add capacity and operational flexibility, and support reliable service as community and customer needs change over time.
Project Benefits
What the project delivers
-
Reliable service
Improves reliability for local homes and businesses.
-
Regional growth
Creates opportunity for growth in northwest Indiana.
-
Community development
Assists in attracting and supporting community development.
-
Uninterrupted maintenance
Maintenance performed without disrupting power.
Project Schedule
Project timeline
- Fall 2026 Project announcement
- Late Fall 2026 Line route announcement
- Winter 2027 Fieldwork and right-of-way discussions
- 2027 & 2028 Construction
- Fall 2028 In service
Typical Structures
Structures and rights-of-way
The project involves building single steel 69-kV monopole structures.
Project Area
Study area and route options
The proposed route options connect existing transmission lines to the future Bridge Creek Substation. Public input, combined with technical data, will help refine these options.
What is the purpose of this project?
The project will support electric service needs associated with load growth in and around the Hoosier Heartland Industrial Park southeast of Delphi. WVPA is planning a new 69/12 kV substation and related 69 kV tap line connections to strengthen service reliability.
Where will the project be located?
The project is located in the general area of the planned Bridge Creek substation southeast of Delphi, Indiana. Route options are still being evaluated before a preferred route is selected.
Has a final route been selected?
No. The project team is evaluating route options using engineering, environmental, land use, constructability, and right-of-way considerations. Public and stakeholder feedback may help identify local conditions and property-specific information that should be considered during the routing process.
What factors are being considered during route evaluation?
Route evaluation may consider existing land use, parcel boundaries, road and utility corridors, streams, wetlands, floodplain or floodway areas, cultural resources, cemeteries, airports, emergency services, constructability, right-of-way needs, and opportunities to reduce impacts where practicable.
How will landowners and community members receive project information?
Project information may be shared through mailed outreach materials, website updates, targeted stakeholder coordination, and direct communication with affected or potentially affected landowners as the project advances.
How can comments or questions be submitted?
Comments and questions may be submitted through the project website. The project team will review received comments and carry relevant information forward into routing, land acquisition, and construction planning.
Will my property be affected?
Potential property impacts will depend on the final route and right-of-way requirements. If a property is identified as potentially affected, the project team will coordinate directly with the landowner regarding survey needs, access, easement requirements, and next steps.
What is right-of-way?
Right-of-way is the land area needed to safely construct, operate, inspect, maintain, and access the transmission line. The exact width and location will depend on the final route, engineering requirements, existing corridors, and applicable utility standards.
How will easements be handled?
Once the route is better defined, the project team will identify affected parcels, obtain necessary title information, prepare easement documents, and work with landowners through the acquisition process.
When will construction begin?
Construction timing will depend on completion of routing, engineering design, permitting, right-of-way acquisition, material procurement, and other project approvals. Schedule updates will be shared as key milestones are confirmed.
What environmental resources are being considered?
The project team is reviewing environmental and routing considerations such as streams, wetlands, floodplain or floodway areas, and other mapped resources. Additional field review or permitting studies may be completed as the route is refined.
How will you determine where the route will be?
The route will be determined through a routing study that evaluates engineering needs, environmental resources, land use, constructability, existing corridors, parcel impacts, right-of-way requirements, and stakeholder input. At least two feasible route options will be reviewed before a preferred route is selected.
What will the transmission line look like?
The transmission line is expected to be a 69 kV overhead line supported by utility structures selected during detailed engineering. Final structure type, height, span length, and placement will depend on design requirements, terrain, existing utilities, right-of-way conditions, and constructability considerations.
How will this project be funded?
The project will be funded through WVPA’s normal utility planning and capital investment process. Project costs are evaluated as part of system planning to support reliable electric service and future load growth.
How wide of an easement is needed for this project?
The easement width will depend on the final route, structure type, engineering requirements, and whether the line parallels an existing road or utility corridor. 70 feet where the line parallels road right-of-way and approximately 100 feet where it does not. Final easement needs will be confirmed during design and land acquisition.
Is this project being built specifically for data center development?
No. The project is intended to strengthen the local electric system and support reliable service for existing customers and future community and economic development.
How will this project support long-term reliability?
The new substation and related 69 kV transmission connections are being planned as long-term electric infrastructure. They will add system capacity and operational flexibility, help meet projected load growth, and support reliable electric service as customer and community needs change over time and planning for future generations.
Project Materials
Documents and resources
Additional materials will be added as the project moves forward.